Commercial Office

Godrej Fund Managment

Location

Bangalore

Year Completed

2024

Project Duration

6 months

Plant Specification

262 KW

Capacity

Rs. 42 LAKHS

Annual Savings

3 YEARS

Payback Period

390 Tonnes

CO₂ Saved / Year

How We Delivered

The Challenge

A financial services office in Bangalore needed a solar solution that aligned with the ESG principles the firm champions for its investment clients starting with their own premises.

Our Solution

A 262 kW rooftop solar plant, engineered for the building’s load capacity, delivering consistent generation that offsets a meaningful share of the office’s annual electricity consumption.

The Impact

Approximately 3,80,000 units generated annually at a 3-year payback, contributing directly to the firm’s own sustainability reporting and carbon reduction narrative.

Why This Project Matters

“When a fund management firm installs solar, it makes a statement beyond the building. Practising what you preach on sustainability is increasingly what clients, employees and regulators expect.”